Power Distribution for the District Court in Katowice

Commissioned by Cnergy sp. z o.o. for the District Court in Katowice, we will implement the power distribution system along with a metering and billing system.

The scope of our commission includes:

  • 20/0.4kV transformer station including a full set of installations and Health and Safety (OHS) equipment.

  • Main and fire emergency switchboards equipped with a battery system.

  • Distribution boards (Object boards).

  • Metering system.

  • Dedicated ATS (Automatic Transfer Switch) system – this task will be carried out based on the SIVACON S4 switchboard.

Other Projects

MSWiA hospital in Rzeszow – new SYMETRIUM realization!

Our company will perform low-current and BMS automation installations in the expanded block of the MSWiA hospital in Rzeszow, commissioned by Budimex S.A. The newly constructed facility will include a surgical ward, neurology ward, ED, operating theater and helipad.